钢制板式散热器施工大法,请亲惠存!
1、前言
1. Preface
由于钢制板式散热器具有体积小、节省空间、外观美观装饰性好的特点,近几年广泛的应用于工程施工中,经过施工总结,归纳钢制板式散热器安装工法如下。
Because the steel plate radiator has the characteristics of small volume, space saving, beautiful appearance and good decoration, it has been widely applied in engineering construction in recent years. After the construction summary, the induction method for the installation of steel plate radiator is as follows.
2、工法特点
2. Characteristics of industrial law
2.1采暖管道地面敷设时,要在垫层施工前将支管甩口到位,加大水暖施工前期工作量,减小后期工作量,避免竣工前水暖任务重,抢工的现象。
2.1 ground laying heating pipes, to cushion construction before the branch left port in place, increase plumbing pre construction workload, reduce the workload of late, avoid plumbing before the completion of the task is heavy, the phenomenon of emergency.
2.2安装调试简单方便,节省人工。
2.2 installation and debugging simple and convenient, save manual.
3、适用范围
3. Scope of application
适用于民用住宅建筑闭式循环采暖钢制板式散热器安装。
It is suitable for the installation of steel plate type radiator of closed cycle heating for civil residential buildings.
4    施工工艺
4 construction technology
4.1 工艺原理
4.1 process principle
散热器安装是在主体结构验收完,采暖立管安装完毕,墙面抹灰完成后,进行散热器的安装,按照设计及规范要求确定散热器安装位置,栽好托钩或固定支架后将散热器挂上安装,然后进行散热器支管安装,散热器安装完成,最后即可进行系统试压。
The radiator is installed in main structure acceptance, heating pipe installation, wall plastering is completed, the installation of the radiator, in accordance with the design requirements and specifications to determine the installation position of the radiator, planted a supporting hook or the mounting bracket will hang on and then install the radiator, radiator pipe radiator installation, the installation is complete, the pressure test system finally you can.
4.2 工艺流程
4.2 process flow
散热器单组水压试验——托钩和固定卡安装——散热器挂装——支管安装——系统试压
A single set of water pressure test for the radiator - the installation of the hook and the fixed card - the radiator mounting - the installation of the branch pipe - system test pressure
4.3   工法要点
4.3 main points of industrial law
4.3.1施工准备:
4.3.1 construction preparation:
4.3.1.1将散热器抬到试压台上,连接试压泵,打开进水阀门,往散热器内充水,同时打开放气嘴,排净空气,待水满后关闭放气嘴。
4.3.1.1 will be carried to the radiator on testingtable, connect the pressure test pump, open the inlet valve to the radiator with water and open the vent mouth, exhaust air, water to be full closed after discharge nozzle.
4.3.1.2加压到规定的压值后,关闭进水截门,持续2-3min,观察散热器接口板壁阀门有无渗漏,不渗漏为合格。
4.3.1.2 pressure to the specified pressure after closing the water inlet valve, duration 2-3min, observation of radiator valve has no leakage wall interface, no leakage for qualified.
4.3.1.3如有渗漏视情况修理或更换,试压合格后打开泄水阀门,泄净水后将散热器运到安装地点安装。
4.3.1.3 if there is leakage, repair or replace, test the pressure after opening the discharge valve, discharge the water after the radiator to install the installation site.
4.3.2按照设计图纸要求将符合设计规格的散热器运到各房间,根据散热器的尺寸、安装位置及高度在墙上画出安装中心线。
4.3.2 according to the requirements of the design drawings, the radiator that meets the design specifications is transported to the rooms. The installation center line is drawn on the wall according to the size, location and height of the radiator.
4.3.3托钩和固定卡安装:
4.3.3 hook and fixed card installation:
4.3.3.1按设计及规范要求在要安装散热器的墙上画出散热器托钩安装的中心线位置。
4.3.3.1, according to the design and specification requirements, draw the center line of the radiator hooked hook on the wall of the radiator to be installed.
4.3.3.2用錾子或冲击钻等在墙上按画出的位置打孔洞,固定卡孔洞深度不少于80mm(使用膨胀螺栓应按膨胀螺栓的要求深度),打好孔洞将托钩栽好固定。
4.3.3.2 with a chisel or percussion drill on the wall to draw the location of holes, fixing hole depth of not less than 80mm (the use of expansion bolts should be according to the requirements of the depth of the expansion bolt), lay the holes to support hook fixed planting.
4.3.3.3每组钢制板式散热器背板上均在四角焊上带孔的钢板支架,而后将散热器安装在墙上的固定支架上(也可以按照厂家配套的托钩进行安装)。
4.3.3.3 each group of steel plate radiator backplane is welded with steel plate support with holes on the four corners, then the radiator is installed on the fixed support on the wall (also can be installed according to the supporting hook matched by the manufacturer).
4.3.3.4在轻质板墙上,钩卡用穿通螺栓加垫圈固定在墙上,并且保证垫片不能高出装饰墙面。
4.3.3.4 is on the wall of light plate. The hook card is fixed on the wall with a perforated bolt and a washer, and ensures that the gasket cannot be high out of the decorative wall.
4.3.4散热器挂装:将采暖管路冲洗干净后,把钢制板式散热器抬起挂在固定支架上,散热器背面与装饰后的墙内表面安装距离要符合设计或产品说明书要求,如设计未注明,应为30mm。带上垫圈和螺母,紧到一定程度后找平找正,然后拧紧到位。
4.3.4 radiator installation: after heating the heating pipeline, the steel plate radiator is lifted up and hung on the fixed support. The distance between the back surface of the radiator and the interior wall of the decoration must meet the requirements of the design or product specification. If the design is not specified, it should be 30mm. Take the washer and nut, tighten to a certain degree and look for the correct, then tighten it in place.
4.3.5钢制板式散热器的放风门按设计要求由厂家负责配套安装好。
4.3.5 steel plate radiator at the door according to the design requirements by the manufacturers responsible for supporting the installation.
4.3.6支管安装:
4.3.6 branch installation:
4.3.6.1侧进侧出式板式散热器支管安装:分为同侧连接、异侧连接和下进下出异侧连接三种连接方式(如上图所示)。同侧连接方式适用于各种型号的散热器;异侧连接适用于有较大结构长度的散热器,使整个长度能均匀散热;采用下进下出异侧连接方式散热能力要降低10%,因此不建议采用此连接方式。支管由采暖立管甩口位置连接支管至散热器,坡度为1%,坡向利于排气和泄水。
4.3.6.1 side inlet and outlet side plate radiator tube installation: it can be divided into three connection ways: one side connection, opposite side connection and down inlet and outlet side side connection (as shown above). The way of the same side connection is suitable for all kinds of radiator. The opposite side connection is suitable for the radiator with larger structure length, so that the whole length can be evenly dissipating. The heat dissipation ability of the lower down outlet and the opposite side connection mode is reduced by 10%, so it is not recommended to use this connection mode. The branch pipe is connected with the branch pipe to the radiator by the position of the heating riser. The slope is 1%. The slope is favorable to the exhaust and discharge.
4.3.6.2下进下出式板式散热器支管安装:下进下出式散热器支管多数都是塑料或复合采暖管道埋地敷设,在相应位置甩口出地面垫层用钢塑转换接头换金属管与散热器连接,因为下进下出散热器进出口支管过短,尺寸无法调整,支管与散热器接口对接困难,为便于安装,采取在散热器接口处地面预留200mm*300mm管槽的方法,利用塑料管道的柔性保证金属管与散热器接口正常对接(详见散热器支管连接大样图)。支管连接完成后将预留的管槽填实,填堵管沟时要派专人看管散热器支管,防止施工过程中将支管偏离原位,使露出地面的金属管道保持垂直,垫层混凝土凝固后,土建可以进行面层的施工。
4.3.6.2 in and out in the bottom plate type radiator pipe installation: in a branch type radiator is mostly plastic or composite heating pipes buried in the corresponding position, a ground cushion with swing steel plastic adapter for metal tube connected with the radiator, because in and out the radiator import and export branch is too short, can not adjust the size. Docking branch pipe and radiator interface difficulties, in order to facilitate the installation, take in the radiator at the interface of ground 200mm*300mm tube slot reservation method, using the flexible metal tube radiator and ensure normal plastic pipe butt joint interface (see heat exchanger branch connection drawing). After the completion of branch connection will be reserved for the pipe filled, filling pipe ditch to send someone to look after the radiator pipe, to prevent the construction process will deviate from the branch in situ, the metal pipe above the ground to keep vertical bedding concrete construction can be solidified, the surface layer.
4.3.7采暖系统安装完毕,按照设计及规范要求进行系统水压试验,发现渗漏及时处理,直至试压合格。
4.3.7 heating system is installed, according to the design and standard requirements of the system water pressure test, found that the leakage of timely treatment, until the test pressure is qualified.
5  机具设备
5 equipment equipment
表1             机具设备
Table 1 equipment equipment
序号
Serial number
名称
Name
单位
Company
数量
Number
1
One
冲击钻
Percussion drill
platform
1
One
2
Two
管  钳
Forceps
hold
2
Two
3
Three
活动平板扳手
Movable flat wrench
hold
1
One
4
Four
水平尺
Level ruler
hold
1
One
5
Five
卷  尺
Tape measure
hold
1
One
6
Six
铅  笔
Pencil
branch
1
One
6  劳动组织
6 Labor Organization
表2              劳动组织
Table 2 labor organization
序号
Serial number
人员
personnel
人数
The number of
职责
Duty
1
One
技术主管
Technical Supervisor
1
One
负责全面技术质量、工程施工进度的管理
Responsible for the management of comprehensive technical quality and construction progress
2
Two
技术人员
Artisan
1
One
负责专业技术管理
Responsible for technical management
3
Three
工长
Foreman
1
One
组织安排人员进行施工
Organize staff to carry out construction
4
Four
质检员
Inspector
1
One
对工程进行全面质量监督检查
Comprehensive quality supervision and inspection of the project
5
Five
安全员
Security officer
1
One
负责安全管理
Responsible for safety management
6
Six
材料员
Material clerk
1
One
负责材料的采购
Procurement of materials
7
Seven
安装工
Installer
2
Two
一组两人进行散热器挂装和支管安装施工
A group of two people carry on the installation and installation of the radiator and the branch pipe
7  质量控制
7 quality control
表3                 质量执行标准
Table 3 quality implementation standards
序号
Serial number
项  目
Project
执行标准
Standard of execution
1
One
《建筑给水排水及采暖工
Building water supply and drainage and heating workers